April 28, 2026NAMC Advances Ghor Fifa Copper Exploration Ahead of Phase II Drilling
The National Arab Mining and Downstream Industries Company (NAMC) has completed 7.7 kilometres of access roads and 11 exploration trenches at its Ghor Fifa Copper Project, expanding site access and the project’s technical evidence base ahead of Phase II drilling.
Fieldwork Expands Access
Between 18 April and 28 August 2026, access-road construction opened additional areas of difficult terrain for systematic trenching and sampling. Trenches 9 through 19 are now complete, while construction of the access road to Trench 20 remains in progress. NAMC has mobilised an additional trenching machine to accelerate the remaining works.
These activities build on Phase I, during which eight diamond drill holes were completed for a total of 352.4 metres. Exploration work undertaken to date covers approximately 30% of the licence area, leaving a substantial portion for further investigation.
Geological Observations and Laboratory Programme
Field observations have recorded malachite mineralisation within the targeted Nemira Dolomite and Shil Al-Hana units. NAMC has collected 79 rock samples from the completed trenches. The samples are undergoing preparation and analysis under a documented chain of custody, with work conducted through a primary laboratory and results subject to independent laboratory verification.
Initial analytical results have also indicated the presence of gallium, silver and barium. NAMC is evaluating their technical significance and potential economic relevance as the data set develops. The field observations and analytical results remain part of an ongoing exploration programme and do not constitute a Mineral Resource estimate.
Phase II Drilling Preparations
The exploration programme has been extended until 31 January 2027. NAMC has signed a Letter of Intent with a reverse-circulation drilling contractor. Issue of the purchase order remains subject to final confirmation of the drilling plan by the Company’s consultants, and mobilisation is targeted for November 2026.
Based on the final technical recommendation, NAMC is also considering whether part of the geophysical survey budget should be reallocated to additional drilling. Any approved changes will be communicated to the Ministry of Energy and Mineral Resources in accordance with the applicable procedures.
Towards an Initial Mineral Resource Estimate
NAMC has appointed independent technical oversight for Phase II to review the exploration data and future reporting requirements under the JORC Code 2012 Edition.
Phase II is intended to support an initial Mineral Resource Estimate during the first half of 2027. Reporting will depend on sufficient assay results, appropriate drilling density, sampling integrity, quality assurance and quality control, and acceptance of the data by the relevant Competent Person.
The immediate focus is to finalise the drilling plan, complete the remaining access works and mobilise the contractor.